IFB 23-52: 2023 Reconstruction of Curb and Sidewalks at 8 Schools in the City of Lowell

Project DescriptionReconstruction of curb and sidewalks at the following schools:

Butler School (1140 Gorham St)

Shaughnessy Elementary School (1140 Gorham St)

Cardinal O’Connell Early Learning Center (21 Carter St) 

Wang Middle School (365 West Meadow Rd) 

Pawtucketville Elementary School (425 West Meadow Rd) 

Bartlett Community Partnership School (79 Wannalancitt St) 

Moody Elementary School (158 Rogers St) 

Washington Elementary School (758 Wilder St)  

 

Start Date: June 2023


Estimated Completion Date: August 2023


Estimated Cost: $1,140,125


Contractor: PJ Keating


City Contact: Engineer’s Office 

               Phone: 978-674-4070 

                        Email: EngineersDept@lowellma.gov


Status Updates:

6/27/2023: PJ Keating completed demolition of existing sidewalks at the Wang/Pawtucketville Schools on 6/26 and the Bartlett School on 6/27. Washington School demolition will begin tomorrow, 6/28. Sidewalk curbing crews will begin at Wang/Pawtucketville Schools later this week.


8/8/2023: All 8 schools have the majority of the work completed. Remaining tasks include line striping and sign installation in addition to final punch list items. Construction scheduled to be completed the week before start of school.

Project File(s)