Project Description: Repair of existing sidewalks and wheelchair ramps in order to fix hazards and increase ADA compliance concentrated mostly in the downtown area.
Start Date: April 21, 2022
Estimated Completion Date: July 21, 2023
Estimated Cost: $1,032,400.00
Contractor: Richard D’Ambrosia, Inc.
City Contact: Engineer’s Office
Phone: 978-674-4070
Email: EngineersDept@lowellma.gov
Status Updates:
12/1/2022: 33 WCR’s to date have been completed. Work will continue in the spring.
3/30/2023: D'Ambrosia is scheduled to return to Lowell to continue sidewalk and wheelchair ramp reconstruction starting the week of 4/3, weather permitting. Work will begin on Broadway St at multiple wheelchair ramps and deteriorated spans on sidewalk from Willie St to Worthen St over the next month.
6/27/2023: D'Ambrosia completed wheelchair ramps and sidewalk panels along Broadway St, Warren St, Prescott St, and Bridge St over the last three months.
D'Ambrosia is currently working on wheelchair ramps on Paige St and along John St.