Billerica Street Culvert Replacement (Funding Pending)

The City of Lowell is moving forward with the replacement of the culvert on Billerica Street to improve drainage and reduce the risk of flooding. The existing culvert is outdated and will be replaced with a modern structure that meets current standards for stormwater flow and roadway safety. 

The work includes culvert removal and installation, utility coordination, roadway reconstruction, and site restoration will be part of this project. 

Project Schedule (Tentative): 

PhaseEstimated date

Survey and Utility Mark outs 

June 2025 


25% design submission 

September 2025 


100% design Submission and Bid Package  

January 2026 


Construction Start 

To be Determined 


 

 

During construction, traffic detours and temporary closures may be required. Advance notice will be provided to residents and businesses. 

Billerica Street