The City has received several requests to construct a new sidewalk along Campbell Drive. In order to determine whether a sidewalk should be a priority investment for the City, a temporary sidewalk trial will be installed along Campbell Drive starting the week of August 4, 2025. This trial is intended to provide a dedicated pedestrian walking area that would imitate the extension of the existing sidewalk on Campbell Drive by the Bailey Elementary School. The trial will be in place approximately 60 days, and gather feedback from students, parents, and residents. Vehicle traffic flow will remain as existing along Campbell Drive, with one-way flow during drop-off and pick up periods. Feedback is being collected here: Campbell Drive Survey Link
Below outlines the results of the survey conducted in May 2024:




The responses based on the respondent’s address were also evaluated. The question was “Would you like the City to construct a sidewalk on one side of…”
Campbell Drive – 17 responses – 6 yes, 11 no (35%/65%)
Fleming Street – 5 responses – 5 yes, 0 no (100%/0%)
St Paul Street – 9 responses – 1 yes, 8 no (11%/89%)